单选题

You work in a company which uses SQL Server 2008. You are the administrator of the company database. Now you are in charge of a SQL Server 2008 instance which contains multiple Agent jobs. The jobs run each job on each day of the week by using seven shared schedules. You must make sure that a job named Job4 doesn';t run Wednesday.  So what action should you perform to achieve this goal?()

发布日期:2021-03-17

You work in a company which uses SQL Server 2008. ...
A

You should remove the schedule for Wednesday from Job5.

B

You should add a new Job5 schedule for Wednesday and disable it.

C

You should delete the schedule for Wednesday.

D

You should disable the schedule for Wednesday.