ompany.com has recently received a new p5-570 in the data center and wants to connect it to an existing HMC environment where each of the existing POWER5 servers has been assigned a static IP address. Which of the following actions should the technical specialist perform to set the service processor network address for a static IP?()
A customer has budget sign-off to purchase a new p5-550 2-way server to replace their aging 2-way 7025-6F0. They like the advantages of the Simultaneous Multi Processing (SMT) ability of this server. Their application is certified at AIX 5.2 and is scheduled for AIX 5.3 certification in six months. The Chief Information Officer is concerned that they will lose the budget if they do not purchase the server this fiscal year. What is the most relevant and cost-effective advice the pSeries technical specialist can offer?()
A customer has a new p5-550 running AIX 5.2 that is SAN-attached to a FAStT900. They have encountered hangs lasting over a minute on their new system during application load testing. They called the pSeries technical specialist for advice. Which of the following would be the most appropriate questions to determine their next step in resolving the problem?()
Company.com has recently received a new p5-570 in the data center and wants to Micro-Partition the server. The customer already has an existing HMC connected to a p690. Which of the following actions should the technical specialist take?()
ompany.com has a Micro-Partitioned p5-570 4-way with six application partitions and two VIO servers. Each VIO server has been allocated 0.5 CPU and the application servers have been allocated 0.4 CPUs. The marketing department wants to deploy a new Web server to support the release of a product. The systems architect has recommended that the Web server will require a whole CPU. Which of the following should the technical specialist suggest to provide the most cost-effective deployment?()
The customer has recently installed a pSeries p5-570 with EMC attached disk storage. After installation, the customer complained that the disk access appeared to be too slow. How should the pSeries technical specialist best assist the customer?()
The account team designed a p5-570 solution to strategically position the customer for future IBM announcements. The customer was dissatisfied upon implementing the solution. An AIX v5.1 partition was added to the requirements halfway through the solution design process and it was not considered in the final design. What should the pSeries technical specialist have done to prevent this situation?()
Company.com has a p5-570 with an application running on each of three Micro-Partitions. The disk I/O is shared through a VIO server. A technical specialist has been asked to upgrade the VIO server. Which of the following procedures should be taken to maintain the integrity of the partitions?()
Which of the following is required to connect a partitioned p5-550 to a modem?()
A customer has requested a proposal for a p5-520 with AIX 5.2 and Sysback. There are no plans to run LPARs or Micro-Partitions on the p5-520 in the near future. The customer has asked the pSeries technical specialist to recommend anything else that may be needed. Which of the following should be recommended in this situation?()