Companycom is planning on upgrading from a pSeries S85 running AIX 4.3.3 to a p5 570 with an HMC. The new server will run AIX 5L 5.2. What should be performed prior to the migration?()

发布日期:2020-04-10

Companycom is planning on upgrading from a pSeries...
A

Verify the ISV application runs on AIX 5.2

B

Power4 to POWER5 upgrades are not supported without a application recompile

C

Check the placement and size of the boot logical volume and disk space requirements on the S85

D

AIX 4.3.3 to AIX 5L 5.2 migrations are perfectly compatible so nothing needs to be checked