移动端

  • 题王微信公众号

    题王微信公众号

    微信搜“题王网”真题密题、最新资讯、考试攻略、轻松拿下考试

多选题

Refer to the exhibit. Two routers are connected by Frame Relay and are running OSPF bet ween them. Each router has been configured with the appropriate network statements under router ospf 1, but the routers are not forming an adjacency. Which of the following three commands could be configured on each router to correct this problem?()

发布日期:2021-01-28

Refer to the exhibit. Two routers are connected by...
A

RouterC(config - if)#ip ospf network broadcast   RouterD(config - if)#ip ospf network broadcast

B

RouterC(config - if)#ip ospf network point - to - point   RouterD(config - if)#ip ospf network point - to - point

C

RouterC(config - router)#neighbor 10.100. 100.4   RouterD(config - router)#neighbor 10.100.100.3

D

RouterC(config - router)#neighbor 10.255.255.254   RouterD(config - router)#neighbor 10.255.255.253

题王网让考试变得更简单

扫码关注题王,更多免费功能准备上线!

此试题出现在

CMS专题

CMS专题

去刷题
热门试题热门资讯 相关试题

公共卫生突发事件可依据()分类。

老年人和儿童在应用抗菌药时,最安全的品种是()

某建设单位新建办公大楼,将机电设备安装工程发包给A公司,合同约定工程材料由A公司采购,工程设备由建设单位自行采购。A公司将智能化工程和虹吸雨排水工程分别进行了专业分包。自有施工队伍按给排水、电气和通风空调三个施工队分别进行施工部署。根据土建施工单位提供的网络计划,项目部召集相关单位和人员召开协调会,明确了主要工序施工时间节点,编制了施工组织设计,排布了机电安装工程施工网络进度计划,分专业拟定了设备、材料进场计划。提交业主和监理单位,获得批准。 施工期间,发生了如下事件: 事件1,由于场外预制的空调风管运输途中因汽车开行不慎毁坏庄稼与村民发生矛盾,导致风管无法进场,对给排水和电气专业施工也造成了相应影响。经多方协调,风管得以进场,比原计划进场时间滞后2日;相关专业调整了部分工作,最终将对总工期的延误减少到1日。 事件2,按既定网络计划,土建施工单位通知A公司项目部,空调机组设备基础将于1周后施工,但由于设备品牌和选型迟迟没有确定,设计图纸滞后,地脚螺栓无法定位。经协调,在原定设备基础施工时间5日后拿到了空调机组施工图,相关专业调整了部分工作,最终将对总工期的延误减少到2日。 分别说明两起事件是否能够得到工期和费用索赔?说明原因。

故事中,皮皮两次去干什么?()

转速限制环节和负荷限制环节在主机转速控制系统中的控制位置是()。

学生上完一节课后,不受该课内容的影响,自觉做好上第二节不同内容课的准备。这种注意品质是(  )。

潜水泵在使用完毕后要注意好封装保存。在保存前,首先放净()内部的清水,擦干表面。

偏移命令是()

人力资源甄选中最关键一步是()。

点M沿平面曲线运动,在某瞬时,速度大小ν=6m/s,加速度大小a=8m/s2,两者之间的夹角为30°,如图4-38所示,则点M所在之处的轨迹曲率半径ρ为()m。

暂无相关推荐~